Project name replaced by project template name

A

Annukka

I am using Project 2007, and I have a problem with the Data Analysis views of PWA. In the Task List field of the EPM Timesheet cube, the Task List Level 02 normally displays the name of the project. In some of my projects however, the name of the project template is displayed instead.

The same can be seen in the Task Updates view: the project name is replaced by the template name. Could someone tell me how to fix this?

..Annukka
 
A

Annukka

The problem was solved as I looked at the File Properties in Project Professional. In the Title field, I replaced the template name by the project name, and now it works. Still I have no idea why the template name was there in the first place...
 
G

Gary L. Chefetz

Annukka:

When you don't provide a title or before you provide one, the system uses
the filename as the title. When you generate new projects, you should always
enter the title and other information in the properties dialog as this
information also articulates to reports in the system.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


in message news:[email protected]...
 