D
DKirkman
Hi,
I know I'm doing something wrong here. Let me explain my situation. I have set my calendar up to reflect a 6.5hr work day.
I have multiple tasks assigned to a particular resource that start on the same day but have differing durations. One task is 20h of effort, the other task is 60h of effort. I would like for the resource to work for 3 hours/day on the 60hr task and 3.5 hours/day on the 20hr task until the tasks are complete but project insists on scheduling the 20 hr task to 7.5hr/day. when I try to manually allocate the tasks and arrange them the way I want. I get one of the tasks highlighted in red indicating that the units assigned are over 100%.
Why is project allocating 7.5h/day when my workday is only 6.5? what am I doing wrong and why won't it let me manually allocate the tasks to fit the 6.5h workday?
Please help, I'm at my wits end.
I know I'm doing something wrong here. Let me explain my situation. I have set my calendar up to reflect a 6.5hr work day.
I have multiple tasks assigned to a particular resource that start on the same day but have differing durations. One task is 20h of effort, the other task is 60h of effort. I would like for the resource to work for 3 hours/day on the 60hr task and 3.5 hours/day on the 20hr task until the tasks are complete but project insists on scheduling the 20 hr task to 7.5hr/day. when I try to manually allocate the tasks and arrange them the way I want. I get one of the tasks highlighted in red indicating that the units assigned are over 100%.
Why is project allocating 7.5h/day when my workday is only 6.5? what am I doing wrong and why won't it let me manually allocate the tasks to fit the 6.5h workday?
Please help, I'm at my wits end.