O
Oludan
I am having trouble with a particular Microsoft project plan. We are on
Project Server 2007 and I am using Microsoft Project 2007 professional on
Windows XP Pro.
Lately, I have being unable to save my changes to ghant chart view, and
whatever data I try to save. REsouces enter their time via OWA to this
project, and I have acccepted the tiemsheet, but the timeshees data are not
getting populated in this project.
Now the ghant chart view that I have has multiple duplicates columns such as
duplicate start/finish dates, duration, actual work, work, actual cost, cost,
and resources column. whenever I tried to hide columns to fix the view, it
worked until next time I open the project then I have to fix it over again.
Questions:
1. Any idea why this could be happening?
2. If I copy the tasks from that project and paste into a new project, will
that mess up the project server or anything in the Enterprise? And, will
resources still be able to enter time against the new project?
Thanks.
OD
Project Server 2007 and I am using Microsoft Project 2007 professional on
Windows XP Pro.
Lately, I have being unable to save my changes to ghant chart view, and
whatever data I try to save. REsouces enter their time via OWA to this
project, and I have acccepted the tiemsheet, but the timeshees data are not
getting populated in this project.
Now the ghant chart view that I have has multiple duplicates columns such as
duplicate start/finish dates, duration, actual work, work, actual cost, cost,
and resources column. whenever I tried to hide columns to fix the view, it
worked until next time I open the project then I have to fix it over again.
Questions:
1. Any idea why this could be happening?
2. If I copy the tasks from that project and paste into a new project, will
that mess up the project server or anything in the Enterprise? And, will
resources still be able to enter time against the new project?
Thanks.
OD