A
akm
When open msp2007 file get error message below...
"No calculations can be performed now.
There is a circular relationship in task 295.
The successors of this task refer back to this task or its predecessors,
causing a circular reference.
To remove the link that is causing the circular reference, select the two
tasks that are causing the circular link, and then click Unlink Tasks on the
Standard toolbar."
When go to the task (295, last task of project) there are no links and if
delete the task, the error message appears (when open project) again with
reference to another task that has no links.
Project is also (assume because of above) not re-calculating when change
dates at tasks (have options set to automatic re-calc).
Ideas ?
Thank you for your help.
akm
"No calculations can be performed now.
There is a circular relationship in task 295.
The successors of this task refer back to this task or its predecessors,
causing a circular reference.
To remove the link that is causing the circular reference, select the two
tasks that are causing the circular link, and then click Unlink Tasks on the
Standard toolbar."
When go to the task (295, last task of project) there are no links and if
delete the task, the error message appears (when open project) again with
reference to another task that has no links.
Project is also (assume because of above) not re-calculating when change
dates at tasks (have options set to automatic re-calc).
Ideas ?
Thank you for your help.
akm