I've seen many tid bits on integration between Project & Outlook, but I have never been able to accomplish much myself. What I'm really trying to do is, when assigning a resource to a task in Project, have that task show up in Outlook on their Task List. Is this even possible? If so, can someone help me out or point me to some resources that can help

Thanks.
 
S

Sean

Mike:

If you're using Project 2003, Outlook integration with
PWA allows task integration with Outlook Calendar not
with Outlook Tasks. If you just want to show the tasks
in your task list, copy and paste.


Hope this helps!

---------------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com
-----Original Message-----
I've seen many tid bits on integration between Project &
Outlook, but I have never been able to accomplish much
myself. What I'm really trying to do is, when assigning
a resource to a task in Project, have that task show up
in Outlook on their Task List. Is this even possible?
If so, can someone help me out or point me to some
resources that can help?
 
S

Shawn

Sean - I have had issues integrating project 2000 with
outlook 2002. Project team members have run WGsetup.exe
and receive task assignments I have initiated in project
via teamassign. However, the MS project help states the
following "Double-click a TeamAssign message to open it.
When you accept the assignment and reply to the message,
the task is added to your task list in Microsoft
Outlook." The task is not being added to users outlook
tasks. Any suggestions?
 