D
David F-H
We are running Project Server 2007 / SQL Server 2005. I have (as Project
Server
Administrator) imported a project and set the owner to another Project
Manager. However, when team members submit task updates I receive
notifications (as well as the project owner). The Project Owner has since
accepted the updates, yet they still appear under Approvals > Task Updates
for myself?
I believe this may be caused by the fact that although I assign a new
Project Owner
after I import the plan, that I am still listed as the Status Manager
against each of the individual tasks. Is the solution to open Project
Professional after I import the plans, and change the Status Manager on every
task (by inserting the Status Manager column) to the project owner? Is there
a better way to achieve this?
Thanks.
Server
Administrator) imported a project and set the owner to another Project
Manager. However, when team members submit task updates I receive
notifications (as well as the project owner). The Project Owner has since
accepted the updates, yet they still appear under Approvals > Task Updates
for myself?
I believe this may be caused by the fact that although I assign a new
Project Owner
after I import the plan, that I am still listed as the Status Manager
against each of the individual tasks. Is the solution to open Project
Professional after I import the plans, and change the Status Manager on every
task (by inserting the Status Manager column) to the project owner? Is there
a better way to achieve this?
Thanks.