If you assign a generic resource and don't name it and if you are the project
owner, it assigns the task with generic resource to you. I have reoccurring
meetings in my project schedule assigning Project Manager(myself) and
Business Analyst(Generic).
When importing tasks it put two assignment tasks on my outlook calendar...
How can I avoid this or is there a better way to do this? Thanks.