Project P edited Actual Work field are not summed with PWA times

V

Veronica

Hi,
How to sum the Actual Work field added manually in Project Proffessional
Project Plan with the one added from resources in PWA? I have tried both
adding the hours connected to the reporting resource in Project Proffessional
Plan (Resource Usage view and/or Task Usage view) or just have them as a
total sum connected to the task. But the hours are overwritten from PWA the
first time the resource reports hours on the task. I want to have the history
of the actual work for the resource too when start to time report from PWA.
Thanks
 
D

Dale Howard [MVP]

Veronica --

When you manually enter Actual Work in the Microsoft Project plan, you must
republish the assignments using the following steps:

1. Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

Hope this helps.
 