V
Veronica
Hi,
How to sum the Actual Work field added manually in Project Proffessional
Project Plan with the one added from resources in PWA? I have tried both
adding the hours connected to the reporting resource in Project Proffessional
Plan (Resource Usage view and/or Task Usage view) or just have them as a
total sum connected to the task. But the hours are overwritten from PWA the
first time the resource reports hours on the task. I want to have the history
of the actual work for the resource too when start to time report from PWA.
Thanks
How to sum the Actual Work field added manually in Project Proffessional
Project Plan with the one added from resources in PWA? I have tried both
adding the hours connected to the reporting resource in Project Proffessional
Plan (Resource Usage view and/or Task Usage view) or just have them as a
total sum connected to the task. But the hours are overwritten from PWA the
first time the resource reports hours on the task. I want to have the history
of the actual work for the resource too when start to time report from PWA.
Thanks