We've been running Project Pro 2003 for the past 11 months. Recently I've
found cases where individuals have as many as 40 - 50 hours A DAY in Actual
Work Protected in the project plans files (seen via resource usage view)!!!
My understanding is this field can only be populated by the approval of
timesheets. When I view resource assignments for these individuals they
typically show a normal workload? How can PWA resource assignments show 8 hrs
in a day while the Actual Work Protected value in the project plan is so
totally whacked?
found cases where individuals have as many as 40 - 50 hours A DAY in Actual
Work Protected in the project plans files (seen via resource usage view)!!!
My understanding is this field can only be populated by the approval of
timesheets. When I view resource assignments for these individuals they
typically show a normal workload? How can PWA resource assignments show 8 hrs
in a day while the Actual Work Protected value in the project plan is so
totally whacked?