D
DV
How do I solve this issue with MS Project. Here we don't
want the schedule of Project Plan to be changed even
if a resource adds time in the timesheet which may
exceed the actual hours that need to be worked. In other
words, if a project manager has posted a task to be
finished in 40 hours and the resource fills in 30 as
actual hours and fills in 30 more as remaining hours.
This means that he is extending his schedule. This
normally shows as an error which is okay. But what I need
to do in MS Project is, what constraints do I use (
fixed duration, fixed units or what ) so that the
schedule of the Project Plan remains as it is even though
the users/resources time outside their actuals.
Thank you in advance.
DV.
want the schedule of Project Plan to be changed even
if a resource adds time in the timesheet which may
exceed the actual hours that need to be worked. In other
words, if a project manager has posted a task to be
finished in 40 hours and the resource fills in 30 as
actual hours and fills in 30 more as remaining hours.
This means that he is extending his schedule. This
normally shows as an error which is okay. But what I need
to do in MS Project is, what constraints do I use (
fixed duration, fixed units or what ) so that the
schedule of the Project Plan remains as it is even though
the users/resources time outside their actuals.
Thank you in advance.
DV.