R
Ripper
We have a proposal to utilize resource substitution to assign resources based
on project priority. We want to do this at project manager level but the
project manager can not see all affected projects or resources. I have 3
questions.
1. Can this be done without giving the PM enterprise authority?
2. Will there be a system impact if I have 10,000 resource in the pool and
4,000 projects?
3. Can anyone give me the ammunition to shoot this down?
on project priority. We want to do this at project manager level but the
project manager can not see all affected projects or resources. I have 3
questions.
1. Can this be done without giving the PM enterprise authority?
2. Will there be a system impact if I have 10,000 resource in the pool and
4,000 projects?
3. Can anyone give me the ammunition to shoot this down?