Tim Mccoy
I have a master schedule with about 23 sub-projects linked to it. All
projects (and the master resource pool) are located in the same folder on a
network drive. I can open the master schedule and all sub-projects
successfully and verified the sub-projects are all being linked from the
correct location, which is the network drive.
Another user opens the same master schedule and some of the sub-project
links work (pull from the network drive) and others do not work. The master
schedule is trying to pull some of the sub-projects from an invalid link
which is an older link on a c: drive.
I do not understand why this one user is getting different results. Maybe
there is a cache, which I do not understand, the master schedule is pulling
the links from.
Can somebody please advise on a resolution?
Thank you!
Tim
projects (and the master resource pool) are located in the same folder on a
network drive. I can open the master schedule and all sub-projects
successfully and verified the sub-projects are all being linked from the
correct location, which is the network drive.
Another user opens the same master schedule and some of the sub-project
links work (pull from the network drive) and others do not work. The master
schedule is trying to pull some of the sub-projects from an invalid link
which is an older link on a c: drive.
I do not understand why this one user is getting different results. Maybe
there is a cache, which I do not understand, the master schedule is pulling
the links from.
Can somebody please advise on a resolution?
Thank you!
Tim