hi all,
I have found a strnge behaivour of MS Project Pro 2007...
if I assign a resource to a milestone (duration ZERO), MS project Pro
will give to the cost of 1 hour.... why???
the only way to give the cost ZERO, is to insert manually Unit 0
0%....
I know that the mileston don't need to be assigned to anyone... but
why this appen????
I though that the cost was linked to the "Work", not to the Unit....
does anyone know why???
thanks
Vit