PRoject Pro 2007 and resources on milestone...

V

Vit

hi all,

I have found a strnge behaivour of MS Project Pro 2007...

if I assign a resource to a milestone (duration ZERO), MS project Pro
will give to the cost of 1 hour.... why???

the only way to give the cost ZERO, is to insert manually Unit 0
0%....

I know that the mileston don't need to be assigned to anyone... but
why this appen????

I though that the cost was linked to the "Work", not to the Unit....

does anyone know why???

thanks

Vit
 