N
nick_cam
Hi,
I recently encountered a problem when trying to Sync to Protected
Actuals. When loading a plan Project Pro would prompt with a dialog to
Sync to Protected Actuals - if selecting to do this then Project Pro
crashes and exits.
I got around the problem by taking an earlier version of the plan and
reloading it. This fixed the problem, although we did have to backdate
some actuals. I just noticed another user on this group had the same
problem and did the same to fix it.
I was wondering whether there was a more elegant way to get around
this, or any way to prevent this happening in the first place?
We're running Project Pro SP1 and Server SP1
Cheers,
Nick
I recently encountered a problem when trying to Sync to Protected
Actuals. When loading a plan Project Pro would prompt with a dialog to
Sync to Protected Actuals - if selecting to do this then Project Pro
crashes and exits.
I got around the problem by taking an earlier version of the plan and
reloading it. This fixed the problem, although we did have to backdate
some actuals. I just noticed another user on this group had the same
problem and did the same to fix it.
I was wondering whether there was a more elegant way to get around
this, or any way to prevent this happening in the first place?
We're running Project Pro SP1 and Server SP1
Cheers,
Nick