Dear Friends,
I have 12 template views for MS Project Professioal 2003.These templates are
..mpt. These templates are ready so i want to put them in the server to be
available for all uses . what is the way to import them all.
Thanks in advance :)
 
T

Turki Ben Sumih

Dear mark,
I need only to import Views not Projects, when i tried to import ,i asked me
to fill the project information fields.I think this way of importing
considers the view as project where it asks me to specify the calendar!
Could you please advise me. :)
 
M

Marc Soester

Hi Turki,

Project Professional has an import wizard that allows you to import
exisiting projects and templates to Project Server
You will need to open Project Professional by logging into Project Server
After you have been logged on please go to
TOOLS > ENTERPRISE OPTIONS > IMPORT PROJECT TO ENTERPRIZE
Project will open a Wizard which will lead you through the process of
importing your Template into Project Server.
Please note that you will need to correct user rights to do this task
I hope this helps
 
M

Marc Soester

Hi Turki,

Project Professional has an import wizard that allows you to import
exisiting projects and templates to Project Server
You will need to open Project Professional by logging into Project Server
After you have been logged on please go to
TOOLS > ENTERPRISE OPTIONS > IMPORT PROJECT TO ENTERPRIZE
Project will open a Wizard which will lead you through the process of
importing your Template into Project Server.
Please note that you will need to correct user rights to do this task
I hope this helps
 
M

Marc Soester

Try the following:

Connect to Project Server
open the mpp file
open global template ( make a backup before you open it please, just in case)
go to TOOLS > ORGANISER
The Organiser Pop up window appears
Choose the View Tab and choose your mpp file on the left hand side and your
global template on the right hand side.
Copy the views from the project to the global template.
You may also need to copy tables of the views, depending if you have all the
tables that your view uses in the global template
save the global template. CLose and open Project Professional
You should now be able to view the views under VIEW . MORE VIEWS
Hope this helps
 
T

Turki Ben Sumih

Dear Marc,
i would like to thank you so so so so much , you really helped me.I really
appreciate your cooperation dear,your solution was very helpful for me. :)
Turki, Saudi Arabia :)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top