Project Professional 2007 cost

P

PBlanchard17

Hi, I'm using the trial version of MS project professional 07. I would like
to know if there is a way in the details of the schedule to enter in cost &
quantity of labor, equiptment & material? When I click on a certain project I
would like to see the details of that project and the information above would
pop up. Furthermore, is there a way I can print this information along with
my schedule if I needed to?

Thanks.
 
J

JulieS

Hello PBlanchard17,

You may create work, material, and cost resources in Project 2007
using the Resource Sheet view. If you assign work resources to
tasks, Project will calculate work (labor) as well as cost for that
assignment based upon work * resource cost. Material resources also
have rates and again the cost for the material resource is based
upon assignment to tasks.

I wouldn't say this information will "pop up" but you may add cost
and work fields (as well as many others) to the table (left side) of
most all views. You can certainly print information from the table
(left side) very easily.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 