For some reason your new tasks are starting somewhere after the start of the
workday OR your Project calendar is showing working times on a given day of
X hours while the definition of "Day" on the Tools/Options/Calendar page is
X. Lets say your working time calendar shows hours of work being 8am to
12noon and 1pm to 4pm (a 7 hour workday) but the Options setting for "Hours
per Day" remains at the default value of 8. A task with a duration of 1 day
will translate to a duration of 8 hours (actually 480.0 minutes, durations
are ALWAYS stored and computed in minutes to the nearest 10th). It starts
Mon 27 Mar at 8am but the calendar shows the resources will go home at 4
after putting in 7 hours of time, leaving 1 hour still to be done on the
morning of the 28th before "1 days" worth of work has been completed. Or
perhaps the Project Start time is something other than the start of the
workday, causing task starts to be similarly offset. If you have "Autolink
Inserted or Moved Tasks" turned on (and you absolutely SHOULD NOT) and are
adding the new task after another task that ends at something other than the
exact end of the workday, the resulting link will force the new task to
begin at the moment the previous task ends so only part of a day's work gets
done on the day it starts, leaving the residual to be done the next day.
In the Options menu, View tab, select a date format that includes the time
of day to help you figure out exactly what is going on. Check the setting
of your Project Start Date, Project Calendar, and the Tools/Options/Calendar
menu entries. The "Default Start" and "Default Finish" entries should
correspond to the start and end times of your workday, the "Hours per Day"
and "Hours per Week" settings should match the working hours in a day and
week as defined in your Project Calendar. The Project Start time should
correspond to the start of your workday unless you want all of the tasks to
be offset to start later in the day for some reason.
HTH