C
Casey
The Project Professional can not see vacation hours when doing the
resource leveling on any project other than the Administrative project
that contains the vacation task.
The vacation hours do show correctly in the Resource Center. I
republished the Administrative project and other projects, but I just
can not get the vacation hours synchronized in both PWA and
Professional.
I have PWA 2003 and Project Professional 2003. I have applied SP1.
resource leveling on any project other than the Administrative project
that contains the vacation task.
The vacation hours do show correctly in the Resource Center. I
republished the Administrative project and other projects, but I just
can not get the vacation hours synchronized in both PWA and
Professional.
I have PWA 2003 and Project Professional 2003. I have applied SP1.