G
Garon
We have created a project with three tasks, which have been assigned and
published.
For one of the tasks (Task 1) the assignee (Bill) has updated the status to
say the item is complete. This was approved by the PM.
In our project we now have 3 tasks, 1 is 100% Complete and the other two are
0% complete.
As PM I contact Bill and discuss task status as he is out of the office.
Bill advises me;
The Task 1 update was wrong. It should have been Task 2 100% complete and
Task 1 0% Complete.
I open the project in Project Professional and make the necessary changes.
a) Bill is the assignee for all three tasks
b) I update Task 1 and set the Status to 0% complete
c) I update Task 2 and set the Status to 100% complete
d) I save a republish the project (All Information)
Bill logs into PWA from the remote site and advises that the PWA view has
not changed a bit. That is
a) Task 1 is no longer displayed as it is 100% complete and
b) Task 2 is still showing 0% complete
I call Bill a bunch of names about being dumb and all and then go test it
for my self.
Sure enough after many hours of testing and retesting I get the same results.
I have discovered a clumsy work around for the problem
In Project professional
a) Remove Bill as the Assignee from both tasks
b) Save the project
c) Add Bill back as assignee to both tasks (1 and 2)
d) Make the % complete changes and then republish
e) This then shows Bill (in PWA) that he has two deleted tasks and two new
tasks with the new assignments
i ) Task 1 with 0% complete and
ii) Task 2 with 100% complete (It still shows the task, but shows as
100% complete)
f) If Bill highlights the Deleted Tasks and clicks the "Hide" button the two
Deleted Task and the 100% Complete task all disappear leaving just Task 1 &
Task 3 with 0% Complete.
What I need to know is
1. Is it a fault that Project Professional does not update Protected
Actuals (PWA Actuals) when you set status information in Project Professional
and republish
2. Is there a better work around to the one I have come up with, which is a
nightmare if you have many Tasks to change
3. Have others had the above experience
published.
For one of the tasks (Task 1) the assignee (Bill) has updated the status to
say the item is complete. This was approved by the PM.
In our project we now have 3 tasks, 1 is 100% Complete and the other two are
0% complete.
As PM I contact Bill and discuss task status as he is out of the office.
Bill advises me;
The Task 1 update was wrong. It should have been Task 2 100% complete and
Task 1 0% Complete.
I open the project in Project Professional and make the necessary changes.
a) Bill is the assignee for all three tasks
b) I update Task 1 and set the Status to 0% complete
c) I update Task 2 and set the Status to 100% complete
d) I save a republish the project (All Information)
Bill logs into PWA from the remote site and advises that the PWA view has
not changed a bit. That is
a) Task 1 is no longer displayed as it is 100% complete and
b) Task 2 is still showing 0% complete
I call Bill a bunch of names about being dumb and all and then go test it
for my self.
Sure enough after many hours of testing and retesting I get the same results.
I have discovered a clumsy work around for the problem
In Project professional
a) Remove Bill as the Assignee from both tasks
b) Save the project
c) Add Bill back as assignee to both tasks (1 and 2)
d) Make the % complete changes and then republish
e) This then shows Bill (in PWA) that he has two deleted tasks and two new
tasks with the new assignments
i ) Task 1 with 0% complete and
ii) Task 2 with 100% complete (It still shows the task, but shows as
100% complete)
f) If Bill highlights the Deleted Tasks and clicks the "Hide" button the two
Deleted Task and the 100% Complete task all disappear leaving just Task 1 &
Task 3 with 0% Complete.
What I need to know is
1. Is it a fault that Project Professional does not update Protected
Actuals (PWA Actuals) when you set status information in Project Professional
and republish
2. Is there a better work around to the one I have come up with, which is a
nightmare if you have many Tasks to change
3. Have others had the above experience