Mark --
You must change the default method of tracking progress in Project Server to
enter actuals in the daily timesheet portion of the View my tasks page. To
do so, complete the following steps:
1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the first section, select the "Hours of work done per day or per
week" option
4. In the second section, select the "Force project managers to use..."
option
5. In the third section, select the "Resources should report their hours
worked every day" option
6. Click the Save Changes button
Once you have completed the above steps, you will need to ask your project
managers to open EVERY project and to click Collaborate - Publish -
Republish Assignments to "push" the new method of tracking to each user's
timesheet in PWA. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"