We need to plan for payments for our current projects. I need to forecast
the cost for the entire project for the next 6 months or the remainder of the
project. Is there a report or process that will help me forecast this for our
budgets?
Thanks ..... Laz
 
L

Laz

Can you please give me more detail on the generic recources and what reports
I would use to estimate the cost
 
S

Steve House

Assuming you have resources assigned to the tasks and cost rates assigned to
the resources, a "Cash Flow" report will do what you need I think.
 