Each Monday, our management team gets a copy of the project portfolio. The
portfolio is simply a Project Center view showing information about the
project. One of the columns we use is the Baseline Finish column (since we
have our project managers use the baseline feature). However, what happens
when there is a scope change? The project manager could re-baseline over
Baseline0 and wipe out the previous baseline information. Or he/she could
save a new baseline (Baseline1 - Baseline10), but how do I pickup that newer
baseline on my report? If I have a column for Baseline Finish - Baseline10
Finish, my report becomes convoluted. Does anyone have a solution that they
would suggest? I'm looking for a variety of ideas if they're out there.
Thanks
John
portfolio is simply a Project Center view showing information about the
project. One of the columns we use is the Baseline Finish column (since we
have our project managers use the baseline feature). However, what happens
when there is a scope change? The project manager could re-baseline over
Baseline0 and wipe out the previous baseline information. Or he/she could
save a new baseline (Baseline1 - Baseline10), but how do I pickup that newer
baseline on my report? If I have a column for Baseline Finish - Baseline10
Finish, my report becomes convoluted. Does anyone have a solution that they
would suggest? I'm looking for a variety of ideas if they're out there.
Thanks
John