John_JXL
Hello,
I have noticed an inconsistency between the base calendar indicated for a
given resource in PWA under Edit Resource, which is displayed as "Standard",
which is what I expected, as there is only one Enterprise Calendar (standard)
under server settings on PWA.
However if I open MSP 2007, go Tools> Enterprise Options > Open Enterprise
Resource Pool and check out the SAME resource, the base calendar is reported
here as "Standard1".
However I had thought that I was looking at the same information, one way
via PWA the other via MSP 07.
Previous posts suggested that this might be related to the local cache but I
can't see a way of deleting the calendar "Standard1" - I want all resources
to use the base calendar "Standard", which I would maintain via Enterprise
Calendars, but can't work out a way of doing this?
Thanks,
John.
I have noticed an inconsistency between the base calendar indicated for a
given resource in PWA under Edit Resource, which is displayed as "Standard",
which is what I expected, as there is only one Enterprise Calendar (standard)
under server settings on PWA.
However if I open MSP 2007, go Tools> Enterprise Options > Open Enterprise
Resource Pool and check out the SAME resource, the base calendar is reported
here as "Standard1".
However I had thought that I was looking at the same information, one way
via PWA the other via MSP 07.
Previous posts suggested that this might be related to the local cache but I
can't see a way of deleting the calendar "Standard1" - I want all resources
to use the base calendar "Standard", which I would maintain via Enterprise
Calendars, but can't work out a way of doing this?
Thanks,
John.