Project & Resource Calendars (Standard1 & Standard)

J

John_JXL

Hello,

I have noticed an inconsistency between the base calendar indicated for a
given resource in PWA under Edit Resource, which is displayed as "Standard",
which is what I expected, as there is only one Enterprise Calendar (standard)
under server settings on PWA.

However if I open MSP 2007, go Tools> Enterprise Options > Open Enterprise
Resource Pool and check out the SAME resource, the base calendar is reported
here as "Standard1".

However I had thought that I was looking at the same information, one way
via PWA the other via MSP 07.

Previous posts suggested that this might be related to the local cache but I
can't see a way of deleting the calendar "Standard1" - I want all resources
to use the base calendar "Standard", which I would maintain via Enterprise
Calendars, but can't work out a way of doing this?

Thanks,
John.
 
J

John_JXL

Thanks - I tried this but got the message "Project cannot delete the STandard
Calendar, upon which other calendars are based"

I was looking at "checked-out Enterprise Global" calendars - there was only
standard1 listed.

If I look at the specific project plan where the problem was observed, I can
see both Standard and Standard1. If I try to delete this specific project
plan I got the same error message as above.

Is there anything else I could try?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top