Ken Hodson
I have MS Project 2003 and Office 2007. My boss has Project 2003 an
Office 2003. When he opens schedules I've created, the Gantt chart bar
and related logic disappear. All that remains are the entries in th
columns for tasks, start dates, completion dates, predecessors, etc bu
a blank space on the right (even the calendar above is lost).
I didn't see a post addressing this issue, apologies if there is on
already