Project Schedule created in Office 2007 viewed in Office 2003

K

Ken Hodson

I have MS Project 2003 and Office 2007. My boss has Project 2003 an
Office 2003. When he opens schedules I've created, the Gantt chart bar
and related logic disappear. All that remains are the entries in th
columns for tasks, start dates, completion dates, predecessors, etc bu
a blank space on the right (even the calendar above is lost).

I didn't see a post addressing this issue, apologies if there is on
already
 
M

Mike Glen

Hi Ken,

Welcome to this Microsoft Project newsgroup :)

Make sure both PCs with Project 2003 has had SP3 installed. Are you using
Project Pro with Project Server?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 