deluth
I'm currently using MSP2003. I have different resources available at
different times, I set this is the Resource Sheet (General Tab). I then set
all the tasks and assigned it to the resources accordingly. When I level the
resources, Project complained that the unavailable resources were
overallocated. Of course they're overallocated, they're not available to
work yet. Why is Project scheduling them when they're not available? Do I
need to do something special to specify their unavailability?