Brad Harris
I just set up a server and I have saved and publised a dummy project. The
Project users/members are synced up to Active Directory and are members of
the Project. They have tasks assigned to them, however, when they go into
pwa, they can not see their tasks. I can see mine and theirs because I am
the admin. Another member is the admin and she can not see hers either. If
they go into Project center thay can see the project so PWA realizes that
they are associated with the project. If the open the project using PWA and
view assignments , they can see them selves assigned to tasks. Anybody know
why team members are not seeing their assign tasks. P.S. They are not
getting email notifications of task as well.
Project users/members are synced up to Active Directory and are members of
the Project. They have tasks assigned to them, however, when they go into
pwa, they can not see their tasks. I can see mine and theirs because I am
the admin. Another member is the admin and she can not see hers either. If
they go into Project center thay can see the project so PWA realizes that
they are associated with the project. If the open the project using PWA and
view assignments , they can see them selves assigned to tasks. Anybody know
why team members are not seeing their assign tasks. P.S. They are not
getting email notifications of task as well.