Hello,
I want to import the task of Project Server to the Outlook calendar and then
modify the task and update the server.
I succeed on downloading the task in Outlook but when I move the task in the
calendar to another day and then I update the server; the dates
modifications are not transfered on Project server. From Outlook Calendar I
just can modify the number of hours worked on the task.

Do you have the solution ?

Thanks,

Richard
 
B

Brad

Hi Richard,

Only the Master Scheduler using Project Professional can change the dates of
a task. Any changes other than actual work or percentage complete changed by
the user will be overridden by PWA on the next collaboration.

Regards,
Brad
 