Project Server 2003 Performance Question

S

Shawn

Hello. We have a Project Server 2003 environment up and running and the
performance is really slow when you try to open and save projects in project
pro. I know there could be many different reasons for this outside of
Project Server such as hardware and network but I am curious as to what the
limitations are for Project Server. We have about 30 projects in all but
each project is about 3000 lines average. Most of those projects also
contain hundreds of inter-project dependencies to about 5 other projects. We
have about 300 resources in addition to 300 generic resources. We have a few
but not a lot of custom fields and outline codes. So, would it be the size
of the projects, the dependencies within the projects, the number of
resources, or a combination that is likely the cause of the slow performance?
What kind of server architecture would be recommended for this configuration?

Thank you.
 
M

Marc Soester [MVP]

Hi Shawn,

As you meantioned that could have many different reasons. Generally ( and
that is only my personal opinion) I would say that it is a combination of the
way you use your projects and the size.

The way it works in 2003 is that when you open or save a Project, each
single line of your project will be tranfered to your Server, that can be a
fairly long xml file, especially when you have interdepenecy with other
projects.

In order to resolve your Performance issues, you may want to think of load
balancing. I personally would involve professional help from an EPM Partner.
There are great Partners out there that are able to help you.
I hope that helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top