Project Server 2003 performance with large project schedules

D

Dries

One of our clients has a single server installation - A Quad CPU monster
with 4 GByte RAM.

They have very few active users - A maximum of 6-10 concurrent Project Pro
users. However, they have large and complex schedules - At the moment arount
5000 tasks per schedule, with a large number of custom fields, as well as
more than 30 resources assigned per schedule. It is envisaged that some
schedules may grow to 10 000 tasks per schedule.

We are getting puzzling performance problems : It takes as long as 15-20
minutes for a schedule to save. What makes this puzzling, is that when we
take this same database to a modest desktop in our lab, the same schedules
save in 3 minutes or less. This raises some questions, which I hope someone
in the community can perhaps help me with:

1) Has anyone had practical experience with very large project schedules in
Project Pro, saving to Project Server? (5 000 - 10 000 tasks) If so, how
long can we reasonably expect it to save?
2) Any ideas on what could cause the extreme performance problems we are
experencing on the specific server?

Thanking you in advance!

Dries
 
G

Gary L. Chefetz [MVP]

Dries:

With schedules this large, the workstation plays a major role in
performance. One would expect that the network segments in the lab are less
trafficked as well. Look at LAN speed and look at workstation specs for the
slow performance.
 
M

Mike Glen

Hi Dries,

Try posting on the server newsgroup as this one's closing down. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question