Project Server 2003: Role in OLAP cube disappears after rebuilt

J

JIM

Hey,



we run Project Server 2003 SP2a on SQL Server 2005 SP1. For accessing the
OLAP cube database we added a role to the cube in Analysis Manager. Access
to the cube via Project Portfolio Analyzer view and everything else works
fine!!!



But when the OLAP cube is being rebuilt by Project Server (automatically or
manually) the roles in Analysis Manager is deleted or disappears. Thus,
access to Analyzer Views in Project Web Access is not possible anymore.



Do you have a solution or any work-arounds (other than creating a new role
day-by-day)?



Best regards,

JIM
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top