I'm revisiting PS 2003 to compare with (buggy) 2007. We're using the
"Hours of Work Done Per Day or Per Week" option yet the Work Remaining
does not show up on the timesheet. Any insight would be helpful.

Thanks,
Andy Novak
UNT
 
D

Dale Howard [MVP]

Andy --

It's on the task table section on the left side of the View My Tasks page.
It's called Remaining Work. Hope this helps.
 
A

anovak

Andy --

It's on the task table section on the left side of the View My Tasks page.
It's called Remaining Work. Hope this helps.

Actually, Dale it wasn't on the left side at all as compared with
y'alls book for 2003. What I ended up having to do is go to the
timesheet view and add Remaining Work to the view - which was puzzling
to me. Either it comes that way or I had inadvertently removed that
column from the view without making a "_copy" as you suggest.

Thanks,
Andy
 
D

Dale Howard [MVP]

Andy --

If memory serves me correctly from your previous posts in this newsgroup,
you removed it from the View because your PM's didn't want their team
members changing the Remaining Work on tasks. :)
 