R
Rachel
I'm having an issue with Project Server 2007. When I approve a task update
in PWA and/or Project Pro, I am unable to view the Preview screen and the
task progress (percent complete) is not updated in the Project.
Here is the detailed process:
1) Team member is assigned a task in Project Pro
2) Team member inputs actual hours worked in their Timesheet in PWA
3) Team member imports hours from their timesheet in the My Task page
4) Team member saves and submits task updates
5) Task update goes to Status Manager for approval
6) Status Manager goes to Task Updates and selects Preview to view how the
task will update the Project
7) A window pops up to preview the updated project, however the pop-up
screen is blank
8) Status Manager selects Close
9) Status Manager selects tasks and clicks Accept
10) Accepted tasks disappear from the Tasks Update screen, however the task
does not update the Project (the % Complete column remains at 0%)
The process is a little different if you want to approve task updates in
Project Pro, however the outcome is the same - the task is not updated in the
Project. I also tried entering hours (and % Complete) directly into the
Assignment Details Dialog box. The problem still occurred.
Any suggestions?
Thanks,
Rachel
in PWA and/or Project Pro, I am unable to view the Preview screen and the
task progress (percent complete) is not updated in the Project.
Here is the detailed process:
1) Team member is assigned a task in Project Pro
2) Team member inputs actual hours worked in their Timesheet in PWA
3) Team member imports hours from their timesheet in the My Task page
4) Team member saves and submits task updates
5) Task update goes to Status Manager for approval
6) Status Manager goes to Task Updates and selects Preview to view how the
task will update the Project
7) A window pops up to preview the updated project, however the pop-up
screen is blank
8) Status Manager selects Close
9) Status Manager selects tasks and clicks Accept
10) Accepted tasks disappear from the Tasks Update screen, however the task
does not update the Project (the % Complete column remains at 0%)
The process is a little different if you want to approve task updates in
Project Pro, however the outcome is the same - the task is not updated in the
Project. I also tried entering hours (and % Complete) directly into the
Assignment Details Dialog box. The problem still occurred.
Any suggestions?
Thanks,
Rachel