Project server 2007: Different methods for Reporting tasks

  • Thread starter Wilt Thomas Rovira Britton
  • Start date
W

Wilt Thomas Rovira Britton

Hi. We have projects with tasks that need to be reported by different
methods.

Example:
Task 1 = %complete. This is done by a contractor and we dont't care about
the number of hours expent.
Task2 = hours worked by day. This task is assigned to a resource.

How can i configure this in Project 2007? I try to use the collaboration
options and the publish field, but it's difficult to configure the project.
I changed the method to report progress in Project, then i set publish
field=NO for some tasks and publish the project. Is there a way to change
the method for reporting progress task by task? what am i doing wrong?

Thanks,
Wilt Rovira
 
D

Dale Howard [MVP]

Wilt --

What are you doing wrong? Everything to do with tracking. You cannot track
tasks by different methods in the same project. Each project must have a
unique method of tracking for the entire project. Hope this helps.
 
W

Wilt Thomas Rovira Britton

I appreciate very much your help.
It was possible configure a project like this in Project Server 2003 just
changing the method and republishing selected tasks.

Wilt Rovira
 
D

Dale Howard [MVP]

Wilt --

You can't in 2007. Every task uses the same method of tracking progress.
Hope this helps.
 