Wilt Thomas Rovira Britton
Hi. We have projects with tasks that need to be reported by different
methods.
Example:
Task 1 = %complete. This is done by a contractor and we dont't care about
the number of hours expent.
Task2 = hours worked by day. This task is assigned to a resource.
How can i configure this in Project 2007? I try to use the collaboration
options and the publish field, but it's difficult to configure the project.
I changed the method to report progress in Project, then i set publish
field=NO for some tasks and publish the project. Is there a way to change
the method for reporting progress task by task? what am i doing wrong?
Thanks,
Wilt Rovira
methods.
Example:
Task 1 = %complete. This is done by a contractor and we dont't care about
the number of hours expent.
Task2 = hours worked by day. This task is assigned to a resource.
How can i configure this in Project 2007? I try to use the collaboration
options and the publish field, but it's difficult to configure the project.
I changed the method to report progress in Project, then i set publish
field=NO for some tasks and publish the project. Is there a way to change
the method for reporting progress task by task? what am i doing wrong?
Thanks,
Wilt Rovira