I apologize if this is a question that has been answered, although I could not find a similar question via search.
[Background]
Our company uses PS 2007 and have close to 25 project managers constantly updating & revising project plans with changes to milestones and resource needs.
Our resource manager is finding it extremely difficult to keep track of changes to the project plans in order to properly manage resources.
[Question]
Is it possible to enable some sort of email notification to the resource manager when a project plan is updated by a project manager? The resource manager is not the owner of the project plan nor a task assigned in any project plan.
Any information will be greatly appreciated.
I apologize if this is a question that has been answered, although I could not find a similar question via search.
[Background]
Our company uses PS 2007 and have close to 25 project managers constantly updating & revising project plans with changes to milestones and resource needs.
Our resource manager is finding it extremely difficult to keep track of changes to the project plans in order to properly manage resources.
[Question]
Is it possible to enable some sort of email notification to the resource manager when a project plan is updated by a project manager? The resource manager is not the owner of the project plan nor a task assigned in any project plan.
Any information will be greatly appreciated.