N
Nik003
We have just discovered what for us is a major issue.
Project with start date, let's say 01/01/2007
a regular team member goes to enter time on tasks, but he enters time on a
certain task before the project start date, let's say week one of 2006.
System accepts the time entered (first problem), changes start and end dates
(second issue), and adds time in the Work section from the date the resource
entered the time onwards (third issue).
This is major, has anybody else foud this problem? Is there a fix for it?
Project with start date, let's say 01/01/2007
a regular team member goes to enter time on tasks, but he enters time on a
certain task before the project start date, let's say week one of 2006.
System accepts the time entered (first problem), changes start and end dates
(second issue), and adds time in the Work section from the date the resource
entered the time onwards (third issue).
This is major, has anybody else foud this problem? Is there a fix for it?