What is the best way to obtain a report of how many actual hours
resources spent on various tasks for a given time period? In Project
Server 2003, this was completed at Resource Center -> View Resource
Assignments. However, that functionality does not exist in 2007, so
what alternatives are people using? My PMs like to gather monthly
reports about where people spent their time.
Thanks!