M
MSPLearner
When comparing Work, Actual Work and Remaining work in Project Center with
OLAP Cube (Portfolio Analyzer Cube), I see small differences. The differences
seem to point to Work, Actual, Remaining Work NOT captured in the cube for
inactive Resources. That does not make sense. Resources on-board/off-board
all the time in a large program, there work has to accounted for the life of
the program, regardless.
Questions
1) Are inactive Resources filtered out in OLAP cubes (what is the default
rule)?
2) Where can I look for documentation?
3) If indeed (1) is the problem above, what are the steps to change it?
Thanks in advance.
MSPlearner
OLAP Cube (Portfolio Analyzer Cube), I see small differences. The differences
seem to point to Work, Actual, Remaining Work NOT captured in the cube for
inactive Resources. That does not make sense. Resources on-board/off-board
all the time in a large program, there work has to accounted for the life of
the program, regardless.
Questions
1) Are inactive Resources filtered out in OLAP cubes (what is the default
rule)?
2) Where can I look for documentation?
3) If indeed (1) is the problem above, what are the steps to change it?
Thanks in advance.
MSPlearner