Hi all,
I have two problems with Project Server 2007:
1. On the window My Tasks, I see the tasks assigned to me but I can
not see the summary task related to this
For example: I have task Requeriment 1 related with summary task
DESIGN and task Requeriment 1 (no the same task) related with summary
task TESTING. On my list task assigned I see Requeriment 1 twice, one
for DESIGN and the other one for TESTING but I don't know which task
is for DESIGN or for TESTING
2. On the window Assignment Details, the value of task progress is
displayed in units Days but I need display and enter, in units Hours.
Where I can configure this?
Thanks for your help
Alexandra
I have two problems with Project Server 2007:
1. On the window My Tasks, I see the tasks assigned to me but I can
not see the summary task related to this
For example: I have task Requeriment 1 related with summary task
DESIGN and task Requeriment 1 (no the same task) related with summary
task TESTING. On my list task assigned I see Requeriment 1 twice, one
for DESIGN and the other one for TESTING but I don't know which task
is for DESIGN or for TESTING
2. On the window Assignment Details, the value of task progress is
displayed in units Days but I need display and enter, in units Hours.
Where I can configure this?
Thanks for your help