Is there a good tutorial out there on how to setup reports in PS 2007. I
created a Data Analysis report, but I'm not clear on what fields to put in
the report. I'd like to display forecast hours to a team or resource and
then show the actuals that have been logged so far for a particular project.

I don't have any data in the Actual Regular Work column which would be my
first guess where hours from a timesheet should appear.

Thanks,

Colin
 
D

Dale Howard [MVP]

Colin --

I would recommend that you add the Resource Names field to the Row Fields
drop area, and add the Work and Actual Work fields to the Total Fields drop
area. You can add Time to the Column Fields drop area and expand it to the
level of time detail you need to see, such as Days, for example. You will
not see information in the Work and Actual Work columns until your PM's
publish their projects and then the OLAP cube rebuilds. Hope this helps.
 