K
Kerry
Does anyone know what permissions need to be on so my PM's can update
resources? I don't want them to be able to add new resources, just update
working times, etc.. I'm using out of the box groups and categories, for the
most part. With the exception that I changed to PM group specifically not to
be able to add new resources. Since our PM's need to access all projects
across the organization, they all have the PM group, and my organization
category.
According to my documentation there is permission for Edit enterprise
resource data. I found that, in the templates. Changed the PM template to
allow it. Applied the template to a test PM, and still have a permission
problem. Maybe it's something else I set. The interesting part, is that I
can't really see what the edit enterprise resource permission is set to on
the PM. It's in the template, which was applied, but when you look at the PM
in the user view, that permission doesn't display. Any ideas?
resources? I don't want them to be able to add new resources, just update
working times, etc.. I'm using out of the box groups and categories, for the
most part. With the exception that I changed to PM group specifically not to
be able to add new resources. Since our PM's need to access all projects
across the organization, they all have the PM group, and my organization
category.
According to my documentation there is permission for Edit enterprise
resource data. I found that, in the templates. Changed the PM template to
allow it. Applied the template to a test PM, and still have a permission
problem. Maybe it's something else I set. The interesting part, is that I
can't really see what the edit enterprise resource permission is set to on
the PM. It's in the template, which was applied, but when you look at the PM
in the user view, that permission doesn't display. Any ideas?