C
crauch66
Greetings ...
Our recent SP2 upgrade for Project Server 07 negatively impacted the My
Tasks page in PWA. We are no longer able to edit [% Complete].
We are able to edit [Physical % Complete] and [% Work Complete], but this is
not what we need. We need to be able to edit [% Complete] in the PWA My
Tasks page.
This worked brilliantly with SP1.
On the server side:
Task Settings and Display --> Tracking method on the server is "% of Work
Complete"
We are running Windows 08, SQL 08 and Hyper-V, with WSS 3.0 and Project
Server 07.
What could be the dealio? How do we get edit capability back for editing [%
Complete] via PWA My Tasks?
Cheers and Regards!
Our recent SP2 upgrade for Project Server 07 negatively impacted the My
Tasks page in PWA. We are no longer able to edit [% Complete].
We are able to edit [Physical % Complete] and [% Work Complete], but this is
not what we need. We need to be able to edit [% Complete] in the PWA My
Tasks page.
This worked brilliantly with SP1.
On the server side:
Task Settings and Display --> Tracking method on the server is "% of Work
Complete"
We are running Windows 08, SQL 08 and Hyper-V, with WSS 3.0 and Project
Server 07.
What could be the dealio? How do we get edit capability back for editing [%
Complete] via PWA My Tasks?
Cheers and Regards!