Project Server 2007 Task Approval Update Screen

S

Savoy55

Task approval update screen is very different from the 2003 version. Is
there a way to customize or create another view where you could see the
updates by resource instead of by task?
 
D

Dale Howard [MVP]

Savoy55 --

Unlike many other pages in the system, the Project Server administrator
cannot edit the view shown on the Task Updates page. The best you can do as
a PM is to click the Settings pick list button (upper right corner of the
data grid) and choose the Group option. In the Group By pane, click the
Group By pick list and choose the Assigned To field. This will show you the
task updates by resource, then by project and task. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top