Project Server 2007: Task status for budget resources (?)

A

Alexey Abramov

Hi All!
I have created several budget resources (of the work type) and assigned them to the Project Summary task. Then I assign definite amount of work to them (to compare with the forecast values afterwards).
Suprisingly these budget resources' assignments appear on the My Tasks page of the project manager. In addition to that their Progress is displayed as 0% and cannot be changed.
Guess, that is not correct at all that the Budget resources' assignments are displayed on the My Task page?
Please help. Thnx!
 