Project Server 2007 Timesheet: Actual work problem!

V

Vit

hi all,

I have a strange problem: when I create a timesheet, the work and the
actual work column are populated with the same value...

why??? the actual work should not be empty???? what is wrong???? I'm
running the EPM 2007 with the last SP 1...

maybe there is an hotfix after SP 1???

thank you so much

Cheers

Vit
 
M

Marc Soester [MVP]

Hi Vit,

One of the reasons may be if you have already updated your tasks within My
tasks and have this task in your timesheet. Project Server will automatically
update the actual work with the time you entered under my task.
Could this be the reason?
Thanks
Marc
 