Hi,
We are using project server 2007. In our company we have Program
Managers, Project Managers, Team Leads, Team Members. Our requirements is,
Project Manager should be the final approver for Team Members and Team Leads
timesheets. And Program Manager should be the final approver for Project
Managers's timesheet. How can I set this...?


Thanks,
Arun
 
P

Paul Conroy

The timesheet manager is an attribute of each resource which can be set in
the resource centre. This has to be manually entered.
 