Project Server Bloating

A

Akram

I am suffering from Project Server File Bloating, it takes almost 10 minutes
to open this specific project from project server, I tried all the MSP
bloating techniques on the MVP site but with no success, can anyone help on
this.
 
G

Geoff Vernon

Hi Akram,
Check the project's Resource Sheet to see if any of the resources have
replicated.
I've had a few instances of this where a resource will replicate many
(20,000+) times and it causes the project schedule to take an extremely long
time to open.
I fixed it by deleting the replicated resources and saving/publishing the
schedule again.
Don't know what causes it though.....:-(
Cheers.....Geoff
 
G

Geoff Vernon

Further to this, I think I've discovered a reference in the Project 2003 SP2
Fix list that could indicate what was going on.....
Quote: "Local resources are duplicated every time that you save the project -
Local resources that have the same name are duplicated every time that you
save the project."
 