Project Server Calendars

F

FGomes

I am migrating some projects from an old Project server development
environment, to a new production environment. I am facing a problem when i
upload some projects to the new EPM. It tells me that some calendars that are
associated to the projects can not be assumed in the new Project Server
global template. Do you know if there is any alternative not being the manual
creation of those calendars at the EPM prior to doing the upload.

Any help would be appreciated,
 
R

RickD

Unless you are using unique calendars in the old project the only thing you
have to worry about is if the various project calendars have a different work
week/day profile. For instance if your old project has the default calendar
(week=Sunday, day=8 hours and week=40 hours) and you save the old project in
MPS with an enterprise calendar with a week starting Monday, day=7.5 and
week=37.5 the duration of most/all tasks will increase because an 8 hour day
comapsred to 7,5 hour day will cause a 1 day duration to become 1.07 days.
 