FGomes
I am migrating some projects from an old Project server development
environment, to a new production environment. I am facing a problem when i
upload some projects to the new EPM. It tells me that some calendars that are
associated to the projects can not be assumed in the new Project Server
global template. Do you know if there is any alternative not being the manual
creation of those calendars at the EPM prior to doing the upload.
Any help would be appreciated,