gregory
Hi. We will be increasing our daily working time from 7 to 7.5 hours
per day in a few months. I wanted to change the standard calendar
with an effective date (say Jan 1). I was hoping that any projects
would schedule our resources for a 7 hour day until Jan 1 and then 7.5
hours after that.
It doesn't seem to let me end the default work week with an end date
and create a new one. Does anyone know if this is possible to do? We
plan ahead and that would skew our projects quite a bit..
Thanks for any suggestions.
Carole