Buzzy
Recently, (like today), I have been getting an error message when I try to
re-arrange time into other tasks, or add new tasks and hours. The error
states:
"Your action may result in actuals in this project becoming out of synch
with the actuals updated from timesheets.
You can: synch actuals with the Synch actuals command on the Tracking menu,
or synch actuals when you save the project."
Has anyone seen this, and know what can be done to allow the movement of
hours, and the addition of tasks and hours?
I haven't ever come across this error in Projecrt Server.
Thanks in advance,
Brian
re-arrange time into other tasks, or add new tasks and hours. The error
states:
"Your action may result in actuals in this project becoming out of synch
with the actuals updated from timesheets.
You can: synch actuals with the Synch actuals command on the Tracking menu,
or synch actuals when you save the project."
Has anyone seen this, and know what can be done to allow the movement of
hours, and the addition of tasks and hours?
I haven't ever come across this error in Projecrt Server.
Thanks in advance,
Brian