Project Server PSI Resource Calendars

  • Thread starter MacKenzie Mickelsen
  • Start date
M

MacKenzie Mickelsen

Hi I have been working with the PSI for a couple of months now. Currently I
am getting resource information for a given project from the
ProjectDataSet.ProjectResourceRow rows. One of the things that I would expect
to find but haven't is what calendar a specific resource is using. There
simply isnt a field that I can see in rows properties that let me know. In
the ProjectDataSet.TaskRow there is a field TASK_CAL_UID, which will let me
know what calendar a particular task is on but I can't seem to find the same
for the resources. Does anyone know where I can find this or if the PSI
supports such?

Any help would be greatly appreciated.
 
S

Stephen Sanderlin

M

MacKenzie Mickelsen

Thank you for the response Stephen. I am implementing your suggestion now. I
am cruious though, if the resource is only local to the individual project
will it show up the ResourceDataSet?

Thanks
Kenzie
 